The southbound road at the intersection of Buffalo Bend and Wanderlust will be closed from January 2 to January 6 for pavement replacement.
Firewater Cir.: The road and driveways have been fully paved, and the road is now open to traffic. The landscaping crew will be on-site on December 30th and 31st, to restore the parkways along the road. The contractor will water and maintain the sod until it is fully established.
Sweet Spring Court: The road is paved and open to traffic. All driveways, except for two, have been paved. The two remaining driveways are scheduled for installation during the first week of January. The landscaping crew will be on-site on December 30 and 31 to restore the parkways along the road. The contractor will water and maintain the sod until it is fully established.
Spring Creek Ln.: All utilities and services have been installed and tested. At the intersection of Spring Creek Ln. and S Valley Pkwy, the water line still needs to be connected to the main line on S Valley Pkwy. The contractor will excavate to locate the existing water line on Thursday, January 2. One lane on S Valley Pkwy at the intersection with Spring Creek Ln will be closed on January 2 and 3. Further updates regarding the water connection will be provided.
Subgrade will be installed on the eastbound side of Spring Creek Lane on December 30 and 31. Paving is scheduled for the first week of January.
Babbling Brook Dr.: The contractor is working on the manhole at the intersection of Babbling Brook and Buffalo Bend today, resulting in the closure of the northbound lane at this intersection. By the end of the day, the contractor will compact the soil, install the flex base, and open the road entirely till after the holidays.
Starting January 2, Babbling Brook will be fully closed from Buffalo Bend to Silver Cloud for the installation of the sewer line. The contractor has notified affected residents about the closure, and temporary access will be provided to them. More information will be provided about the next steps.