Midway Road Construction Phases

Print

Project Construction Phasing and Duration

Following is the general sequence of construction phasing

Current Construction Phase:

Phase 2A - Construction of South Side of Midway Road from Holfords Prairie to Fire Station #6. Construction Duration for this Phase will be around four  months.

Midway Phase 2A Detail Midway Phase 2A Detour

Future Construction Phases

Phase 2B - Construction of North Side of Midway Road from Holfords Prairie to Fire Station #6. Construction Duration for this Phase will be around four months.

Phase 3A – Construction of North Side of Midway Road from Huffines Boulevard to Holfords Prairie Road. Construction Duration for this Phase will be around four months.

Phase 3B – Construction of South Side of Midway Road from Huffines Boulevard to Holfords Prairie Road. Construction Duration for this Phase will be around four months.


Past Construction Phases:

Phase 1A - Realignment of Midway Road and Holfords Prairie Intersection.

Midway Road Phase 1 Detour DetailMidway Road Phase 1 Detour Overall (1)

Phase 1B - includes the construction of around 300' of eastbound Midway Road, west of the Holfords Prairie intersection. Construction duration for this phase: Monday, Dec. 23, 2019 - Monday, Jan. 13, 2020. 

For Phase 1B of Midway Road reconstruction, the contractor will be opening the intersection of Holfords Prairie and Midway Road for thru traffic going north and south on Holfords Prairie and eastbound on Midway Road. Westbound traffic on Midway Road west of Holfords Prairie Road will be closed.

Midway Phase 2A Detail  Midway Phase 2A Detour 1

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Flash Player Download Flash Player Windows Media Player Download Windows Media Player Microsoft Silverlight Download Microsoft Silverlight Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer